First start

HXD-V1 · updated 2026-11-11

The pre-start checklist, what happens at the first start, which we run with you, the acceptance check and the baseline to record.

Taking a newly installed HXD-V1 to its first dry hydrogen. The first start, and any start after the pipework has been opened, needs a separate procedure to purge air from the lines and check for leaks. We run that procedure with you.

  • BeforeInstallation and connection
  • WhoYour site team with a HydroXpand engineer
How to read this chapter

First timeWork through the checklist, and contact us to schedule the start once every line is met.

Done this beforeAfter the pipework has been opened, use the checklist again and contact us.

On this pageBefore you start

Before you start#

CheckOK when
VentsPURGE and DEPR. run to a safe place outdoors with no valve or cap
DrainDRAIN runs through a liquid trap to the vent system
Gas linesH2 IN and H2 OUT connected. Sample outlet connected or capped
PowerEarthed outlet, 200-240 V AC. ON/OFF switch off
NetworkEthernet connected to the network that the control PC uses
ElectrolysersHXB-V1 units installed and ready to start as described in their handbook
Print the first start checklistOne A4 page: pre-start checks, first start and the baseline record.PDF · A4

What happens at first start#

  • Air is purged from the lines and every joint is leak-checked at operating pressure.
  • The regeneration cycle set in the software is checked. The factory setting (12 h cycle, 6 h heating) is kept unless we advise otherwise.
  • The outlet dew point is watched on the dew point sensor, if fitted, or on an analyser at H2 SAMPLE OUT. Until it reaches the dew point you need, the product goes to vent, not to your process.
  • The start date, the operating pressure and the first dew point readings are recorded.

Acceptance#

Check the following after the start. If all four hold, treat the commissioning as accepted. Regeneration and switching can only be confirmed once the first cycle (12 h at the factory setting) has finished.

Hydrogen leaks
At operating pressure, leak-detection fluid or a hydrogen detector at the H2 IN and H2 OUT fittings and downstream joints shows no bubbles or response. You provide the fluid and the detector.
Pressure
The inlet pressure stays at 9.5 barg or above and the unit does not drop to STANDBY.
Regeneration and switching
During heating the tower reaches the regeneration temperature (150 °C) and switches after cooling to 40 °C or below. No fault stop (FS) or emergency stop (ES) alarm.
Dew point
The outlet dew point is -65 °C or below, read on the dew point sensor (option) or an analyser at H2 SAMPLE OUT.

What to write down#

What you record now becomes the baseline for judging whether performance has changed. Without a baseline you cannot tell, months later, whether regeneration has slowed.

  • The date and who ran it
  • Inlet and outlet pressure and the product flow
  • In the first cycle, the time to reach the regeneration temperature and the highest temperature
  • The outlet dew point and how long it took to get there
  • How those compare with the factory acceptance test figures
  • Any alarm that appeared during commissioning

What this chapter is based on

Resource library →

TroubleshootingA find-by-symptom table, cause-by-cause checks for dew point, pressure, regeneration temperature and drains, the control app's alarm list (ES, FS, WA) and what to send us.
Was this page helpful?

Ask the engineer who built it

If your case is not covered here, send us the operating condition and what you observed. The engineer who designed the system answers directly.