← HXP-an productGuides / Electrode operation

How to run and measure our electrodes

Updated 2026-08-23

Written for laboratories assembling our electrodes into a test cell and measuring performance themselves. When datasheet numbers do not reproduce the cause is usually the measurement condition, so we publish those conditions here.

Updated 23 August 2026

What this note answers

This note covers what to do — and what you do not need to do — after receiving electrodes, the conditions behind each published performance figure, and what to check first when your measurement differs from the datasheet.

It is written for laboratories using HXP-an and HXP-ca electrodes with the HXS-0 test cell. If you are integrating a bare stack into your own balance of plant, ask us for the separate integration document.

As shipped — what you do not need to do

  • Electrodes ship cleaned and dried. No additional pre-treatment is required on your side.
  • There is no assembly orientation. Both faces are identical, so either side can face the membrane.
  • After opening, store the electrodes dry.

Cell assembly

Tightening depends on the hardware

HardwareValue
HXS-0 test cell (supplied by us)M6 · 5 N·m twice then 7 N·m twice (crosswise) · M4 terminals at 1.5–2.0 N·m · no press needed
Your own cellTreat the values above as a reference. They change with gasket thickness and material and with active area

Large-area cells need different compression. Send us the cell design and gasket stack-up and we will work it out with you. Do not carry stack tightening conditions (hydraulic press compression followed by two-stage bolting) over to a single cell.

Common to any cell

ItemValue
Most common failureGaskets. O-rings ride out of their seat and the MEA gasket shrinks inwards, so push them back into place after seating
OrientationAnode at the bottom, cathode on top (electrolyte circulates on the anode side)
InsulationApply a PTFE sheet to the end plates
Fluid connection1/4″ double-ferrule on HXS-0

Operating conditions

ItemValue
Electrolyte0.1 M KOH in deionised water
Temperature50 °C
PressureAmbient
Electrolyte flowApprox. 5 mL/min per cm² of active area

Heating takes time. Start measuring only after the cell has actually reached temperature, not when the setpoint is entered. At lower temperature or concentration the same electrode needs a higher cell voltage at the same current density, so a room-temperature measurement will never line up with the datasheet.

Start-up — there is no separate activation step

There is no separate activation step for a new electrode. Bring the cell to temperature and run it at rated current. That is what we do.

StepItem
1Circulate electrolyte after assembly and bring the cell to temperature
2Ramp to rated current in steps. Recommended but not required (for a stack: 0 → 10 → 20 → 30 → 40 → 50 A, two minutes each)
3Hold at rated current for about 30 minutes until the voltage settles, then start measuring
4First-run checks: no leaks at ports and fittings, stable electrolyte flow, and voltage rising sensibly with current

Measurement sequence

StepTechniqueCondition
T1CP · initial stabilisationRated current · 30 min
T2CP · current hold0.1 A/cm² · 30 s
T3LSVOCV → 1.70–1.75 V · 5 mV/s
T4LoopBack to T2 · repeat twice
T5CV1.0 → 0.4 → 1.8 → 1.0 V · 4 cycles · 50 mV/s
T6OCV30 s
T7CP0.1 A/cm² · 30 s
T8PEISDC bias 1.5 / 1.6 / 1.7 / 1.75 / 1.8 V · 100 kHz → 100 mHz · 10 mV amplitude

If performance is good the instrument hits its current limit before reaching 1.8 V. Lower the upper voltage to 1.70–1.75 V in that case.

If the numbers do not match

  1. Did you stabilise at rated current for at least 30 minutes before measuring?
  2. Did the cell actually reach 50 °C (measured, not the setpoint)?
  3. Is the electrolyte 0.1 M KOH?
  4. Was the tightening torque applied per the hardware spec (HXS-0: 5 N·m twice, then 7 N·m twice)?
  5. Did any gasket move out of its seat?
  6. Which membrane and ionomer did you use?
  7. What measurement mode (galvanostatic, potentiostatic, scan rate) and which active-area basis?

Send us these seven and our engineer will reproduce the same condition and work through the cause with you.

Conditions behind each published figure

Published figureCondition
HXP-an Tafel slope 98.7 mV/dec0.3 M KOH · room temperature · three-electrode
HXS-0 catalogue i-V curve4 cm² active area · 1 M KOH · 80 °C
HXS-2 i-V curve0.1 M KOH · 50 °C · 23-cell full stack
HXS-2 efficiency 88% (beginning of life)0.3 M KOH · 60 °CAn earlier condition than the current recommendation
HXS-2 durability 80.2 µV/h/cell0.3 M KOH · 40 °C · 50 A · 23 cells · 2,281 hoursAn earlier condition than the current recommendation

Every published figure was measured using our HXP-an electrode. Figures taken under different conditions are not comparable, so check which condition a number belongs to before putting two side by side.

Send us your conditions

If your measurement is far from the datasheet, send the seven items above. Our engineer reproduces the same condition and comes back with what differed.

The values here come from our own test conditions. With a different cell design, membrane and ionomer, or test rig, the same numbers may not reproduce. Send us your conditions and we will compare them with ours.